QMEB » DRILLING UNDERWAY AT MYL’S BAWDWIN PROJECT
Exploration Infrastructure & Operations Latest News

DRILLING UNDERWAY AT MYL’S BAWDWIN PROJECT

Myanmar Metals Limited has reported significant progress over the Christmas-New Year period, continuing 2017’s fast pace of work related to the world class Pb Zn Ag Cu Bawdwin project.

Commencement of 2018 Drilling Program

On behalf of MYL’s partner and current tenement owner Win Myint Mo (WMM), MYL has reported that drilling has commenced at Bawdwin. One Diamond Drill rig is already operating and a second Diamond rig and a Reverse Circulation (RC) rig have been mobilised and are on route to the project site.

Due for completion by the end of March, the program comprises approximately 5,000m of RC and diamond drilling and aims to provide sufficient density in the upper portion of the Bawdwin Deposit to justify a classification of “Indicated” in accordance with the JORC Code 2012 edition.

In addition, metallurgical and geotechnical information will be gathered. The program has been designed by CSA Global to suit the next phase of geological modelling and mine design and will be conducted by Titeline drilling. Valentis Resources has been engaged to provide all geological support services on site. MYL will report assay results commencing as they become available commencing from mid-February.

Project Manager Appointed

MYL is also pleased to announce the appointment of experienced Australian geologist Tony Chisnall as Project Manager and Site Representative. Mr Chisnall will work alongside representatives of WMM and senior Valentis staff to oversee drilling and resource development work for the Bawdwin project.

Mr Chisnall is a Member of the Australasian Institute of Mining and Metallurgy and a Competent Person as defined in the 2012 edition of the JORC Code. His career of over 20 years includes senior roles with Western Metals in Australia and Padaeng Zinc in Thailand.

He holds a BSc from Canterbury University in New Zealand and a MSc in Ore Deposit Geology from UWA. His experience working in Thailand is of particular note and will be instrumental in helping MYL advance Bawdwin’s development.

Metallurgical Test Work Underway

In addition to the drilling program, metallurgical test work on composite samples selected from the 2017 drill core is underway.

Up to 250kg of samples are being prepared for analysis by ALS under the guidance of metallurgical consultant Battery Limits. Results are expected by the end of February.

Progress with Government Discussions

MYL and WMM have made substantial progress in discussions with the authorities in Myanmar.

CEO and Chairman John Lamb said, “I am pleased with our progress over the Christmas period and with the positive and constructive nature of the discussions with Myanmar authorities. This dialogue and the overall advancement made to date is encouraging.

“Progress towards our goal to develop what is one of Asia’s most significant and under-developed zinc, lead and silver mines at Bawdwin remains well and truly on track.”

Discussions are continuing with both the Ministry of Natural Resources and Environmental Conservation (MONREC) and the Myanmar Investment Commission (MIC), and the Company is taking the necessary steps to fulfil and comply with regulatory and other requirements in order to obtain necessary project approvals.

Add Comment

Click here to post a comment

Gold/Silver Index